About Wowrack Tukwila (SEA)
Wowrack Tukwila (SEA) is a colocation data center operated by Wowrack at 12201 Tukwila International Blvd in Seattle, WA. It's one of 17 facilities we track in the Seattle market, a tier 2 market.
The building is 18,000 sq ft. The site has 3 MW of total power. UPS redundancy is 2N and N+1. Generator runtime is 24 hours at full load. Cooling is 390-ton N+1 chiller plant.
On-site interconnection includes Seattle IX. 8 carriers are available.
Worth knowing: Wowrack's own building with 8 carriers including Seattle IX and Megaport. Other providers, including ColoCrossing, resell space here.
- Industry leaders, not a call centerOur team brings 20 to 30 years from major data center platforms, the channel and data center brokerage.
- Pricing in days, not weeksOne request reaches the providers that fit. No chasing reps one by one.
- We negotiate, you signWe know what buyers in this market pay and use it to get you better terms.
Wowrack Tukwila (SEA) key details
Wowrack Tukwila (SEA) compliance
Wowrack reports these certifications and attestations for Wowrack Tukwila (SEA). Ask for current reports during your evaluation.
Wowrack Tukwila (SEA) location
- Address
- 12201 Tukwila International Blvd, Seattle, WA 98168
Wowrack Tukwila (SEA) specifications
Checked against Wowrack’s website in November 2026. Where the provider’s own sources disagreed, we left the figure out rather than guess. Providers update specs on their own schedule, so we confirm the current numbers with them before you sign. SCR-DC 00933
Power
Cooling
Network
Security
Building
Is Wowrack Tukwila (SEA) the right fit?
Our read from the published specs, plus what we'd tell you from the inside. We confirm the details with Wowrack before you commit.
Where it fits
- Cabinets, cages and smaller suites, with the services a retail colocation customer expects
- Enterprise workloads and moderately dense racks, up to 20 kW per rack
- Network-heavy workloads with 8 carriers and on-site peering at Seattle IX
Insider advice
- Racks top out around 20 kW. If GPUs are on your roadmap, ask what can be engineered now. Retrofitting liquid cooling later is slow and expensive.
- Ask what the whips can handle. If they're sized only for today's circuit, more power later means new whips and paying install fees again.
- Cross connects are where the margin is. Lock the monthly price per connection for the full term and every renewal.
- Visit day and night. Check lighting, parking and nearby rail, chemical plants, gas lines and flight paths.
Nearby in Seattle
Explore
Work at Wowrack? Send corrections or new specs.