Iron Mountain VA-6 Data Center
11891 Sudley Manor Road, Manassas, VA 20109
About Iron Mountain VA-6
Iron Mountain VA-6 is a colocation data center operated by Iron Mountain Data Centers at 11891 Sudley Manor Road in Manassas, VA. It's one of 96 facilities we track in the Northern Virginia market, a tier 1 market.
The building is 230,000 sq ft, all of it colocation space. The site has 32 MW of critical IT power. UPS redundancy is Block N+1. Cooling is Air-cooled chiller plant; block N+1.
20 carriers are available.
Worth knowing: Newest building on the Manassas campus with its own substation and four halls over 23,000 sq ft each.
- Industry leaders, not a call centerOur team brings 20 to 30 years from major data center platforms, the channel and data center brokerage.
- Pricing in days, not weeksOne request reaches the providers that fit. No chasing reps one by one.
- We negotiate, you signWe know what buyers in this market pay and use it to get you better terms.
Iron Mountain VA-6 key details
- Building size
- 230,000 sq ft
- Colocation space
- 230,000 sq ft
- Total power
- Not published
- Critical IT power
- 32 MW
- Availability
- Not published
- Provider
- Iron Mountain Data Centers
- Market
- Northern Virginia
- Type
- Retail colocation
- Specs checked
- November 2026
Iron Mountain VA-6 compliance
Iron Mountain Data Centers reports these certifications and attestations for Iron Mountain VA-6. Ask for current reports during your evaluation.
Iron Mountain VA-6 location
- Address
- 11891 Sudley Manor Road, Manassas, VA 20109
- Building
- 11891 Sudley Manor Road
Iron Mountain VA-6 specifications
Checked against Iron Mountain Data Centers’s website in November 2026. Where the provider’s own sources disagreed, we left the figure out rather than guess. Providers update specs on their own schedule, so we confirm the current numbers with them before you sign. SCR-DC 00546
Power
Cooling
Network
Building
Is Iron Mountain VA-6 the right fit?
Our read from the published specs, plus what we'd tell you from the inside. We confirm the details with Iron Mountain Data Centers before you commit.
Where it fits
- Cabinets, cages and smaller suites, with the services a retail colocation customer expects
- Network-heavy workloads with 20 carriers
- Regulated workloads that need SOC 2, ISO 27001, PCI DSS and HIPAA
Insider advice
- Get usable kW per cabinet in writing. Providers quote breaker size, and a 30A 208V circuit delivers about 5 kW under the 80% rule.
- Ask what the whips can handle. If they're sized only for today's circuit, more power later means new whips and paying install fees again.
- Ask about priority fuel delivery contracts, not just tank size. In a regional outage, the sites with priority contracts get fuel first.
- Visit day and night. Check lighting, parking and nearby rail, chemical plants, gas lines and flight paths.