Iron Mountain MIA-1 Miami Data Center

2925 NW 120th Terrace, Miami, FL 33167

Under constructionIron Mountain Data CentersMiamiIron Mountain Data Centers site

  • Retail colocation
  • Verified November 2026

About Iron Mountain MIA-1 Miami

Iron Mountain MIA-1 Miami is a colocation data center operated by Iron Mountain Data Centers at 2925 NW 120th Terrace in Miami, FL. It's one of 16 facilities we track in the Miami market, a tier 2 market.

The building is 150,000 sq ft. The site has 26 MW of total power and 16 MW of critical IT power.

Security includes 24/7/365 on-site monitoring.

16 MW customer IT load; 26 MVA total redundant power; 100% matched renewable power.

  • Industry leaders, not a call centerOur team brings 20 to 30 years from major data center platforms, the channel and data center brokerage.
  • Pricing in days, not weeksOne request reaches the providers that fit. No chasing reps one by one.
  • We negotiate, you signWe know what buyers in this market pay and use it to get you better terms.

Iron Mountain MIA-1 Miami key details

Building size
150,000 sq ft
Colocation space
Not published
Total power
26 MW
Critical IT power
16 MW
Availability
Under construction; Iron Mountain targets 2026 completion
Market
Miami
Type
Retail colocation
Specs checked
November 2026

Iron Mountain MIA-1 Miami compliance

Iron Mountain Data Centers hasn't published certifications for this facility. We'll request SOC 2, ISO 27001, PCI DSS and HIPAA reports with your quote.

Iron Mountain MIA-1 Miami location

Address
2925 NW 120th Terrace, Miami, FL 33167

Iron Mountain MIA-1 Miami specifications

Checked against Iron Mountain Data Centers’s website and spec sheet in November 2026. Where the provider’s own sources disagreed, we left the figure out rather than guess. Providers update specs on their own schedule, so we confirm the current numbers with them before you sign. SCR-DC 00541

Power

Total power26 MW
Critical IT power16 MW

Cooling

Renewable energy100%

Security

Physical security24/7/365 on-site monitoring

Building

Facility typeColocation
Building size150,000 sq ft
Tier designIII

Is Iron Mountain MIA-1 Miami the right fit?

Our read from the published specs, plus what we'd tell you from the inside. We confirm the details with Iron Mountain Data Centers before you commit.

Where it fits

  • Cabinets, cages and smaller suites, with the services a retail colocation customer expects

Insider advice

  • Get usable kW per cabinet in writing. Providers quote breaker size, and a 30A 208V circuit delivers about 5 kW under the 80% rule.
  • Ask what the whips can handle. If they're sized only for today's circuit, more power later means new whips and paying install fees again.
  • Ask about priority fuel delivery contracts, not just tank size. In a regional outage, the sites with priority contracts get fuel first.
  • Visit day and night. Check lighting, parking and nearby rail, chemical plants, gas lines and flight paths.

Nearby in Miami

365 Boca Raton3500 NW Boca Raton Blvd., Boca Raton, FL
Not published
Verified Nov 2026
365 Data Centers Fort Lauderdale3250 W Commercial Blvd., Fort Lauderdale, FL
Not published
Verified Nov 2026
CoreSite MI1 Miami2115 NW 22nd Street, Miami, FL
Not published
2N UPS
Verified Nov 2026
CoreSite MI2 Miami2100 NW 84th Ave, Doral, FL
103,000 sq ft
2N UPS
Verified Nov 2026
All Miami Data Centers

Explore

Work at Iron Mountain Data Centers? Send corrections or new specs.